Lead time gap

Suppliers promise a lead time. Compare it with how long deliveries really take.

Try this lesson free →
About 5–10 minutes · no sign-up needed

The idea

Suppliers promise a lead time. Compare it with how long deliveries really take:

Formulas

Actual − Promised

Key points

Lead time gapHow much longer deliveries really take than promised.
Work it outTake the promised lead time away from the actual lead time.
Use itPlan with the actual lead time, and hold extra stock to cover the gap.

An unreliable supplier quietly breaks every reorder point that depends on them.

Practice

Try each one in your head first, then open the answer.

1. How many weeks late is Delta Power, on average?
4.2 − 3 = 1.2 weeks
2. In D5, work out Nordic Mounts' lead time gap: actual − promised.
=C5-B5
3. Tap the supplier with the biggest lead time gap.
Nordic Mounts takes 1.5 weeks longer than promised.
4. Delta Power's product sells 250 a week. The plan used a 3-week lead time, but it really takes 4.2. How much extra stock covers the difference?
(4.2 − 3) × 250 = 300 units