Lessons › Retail Supply Chain › Distribution and launches
Retail Supply Chain lesson
DC to store deployment
One UK region: a distribution centre (DC) holding 300 units, and four stores. Each store should reach 4 weeks of cover.
Try this lesson free →The idea
One UK region: a distribution centre (DC) holding 300 units, and four stores. Each store should reach 4 weeks of cover:
Formulas
Weekly sales × 4 − On handKey points
Store needWhat a store needs to reach 4 weeks of cover. Below zero means none.
DC coverHow long the distribution centre's stock would last the stores: 300 ÷ 150 = 2 weeks.
Deploy by needFill the stores closest to running out first.
Deployment decides where stock goes for the last mile, from the DC to the store.
Practice
1. How many units does London need to reach 4 weeks of cover?
60 × 4 − 90 = 150 units2. In D4, work out what Leeds needs to reach 4 weeks of cover. It can't go below 0.
=MAX(0,B4*4-C4)3. Tap the store that needs nothing from the DC.
Manchester already has 5 weeks of cover.4. The DC has 300 units. After sending every store what it needs, how many stay in the DC?
150 + 0 + 90 + 30 = 270 needed, so 300 − 270 = 30 stayLearn it by doing. This lesson is a short hands-on level on Bampaa: see it work, then build and write it yourself, with instant feedback.
Try this lesson free →